12/17/19 Capital Project Update

12/17/19 Capital Project Update
Posted on 12/17/2019

Work week of 12/9/19 – 12/13/19

Phase 2 
o Edger- completed rough insulated metal panel installation and continued with trim out of building exterior,  drywall hanging in office area.
o Brosh - worked on sprinkler and air line rough in, as well as vent and waste for mezzanine mechanical spaces.
o Boland’s- Continued work on fuel island structure.
o Knapp –Complete 90% of light pole bases, electrical rough in inspection complete for offices, continued rough in of mechanical mezzanines.

Phase 3
o FAHS – Continued with tile installation in new band bathrooms and corridors, kitchen equipment was delivered and set up has started, architectural ceiling installation in the kitchen and senior seating area’s is nearing completion, the new sound system for the auditorium continues to progress, painting has started in the new band room and offices, framing is nearly complete in the new FACS sewing room, adjustments were made to locker room lockers and doors.
o Nelcorp – light upgrades G-wing class rooms, install and light kitchen fixtures, kitchen equipment hook up.
o Siracusa – continued with heat runs for the new band area HVAC units, completed duct connections to the new kitchen hood and set diffusers boxes for the architectural celling area’s.
o Syracuse scenery – Has been competing items of the new stage rigging structure as well as installing components of the new sound system.

Work week of 12/16/19 – 12//19

Phase 2
o Edger will continue with exterior trim installation, continue with hanging drywall in the office area and install overhead garage doors.
o Knapp will continue with electrical rough in on the mechanical mezzanine spaces.
o Boland’s will continue with construction of the new fuel island.
o Brosh will continue with  above grade sanitary, venting, domestic water and sprinkler piping

Phase 3
o Siracusa – will set fixtures in the new band area bathrooms, insulate heat pipe on the band area mezzanine and hook up kitchen equipment.
o Nelcorp -  will continue kitchen area lighting and equipment hook up and lighting up grades in the high school wing.
o Fahs – will be completed the remainder of the wood ceilings in the senior seating area, installing terrazzo base in the senior seating area, finishing drywall in the new band rooms , setting up kitchen equipment, starting band area office ceilings, installing bathroom partitions in the band area bathrooms, completing tile in band area and installing high school cafeteria window sills.