3/22/19 Capital Project Update

3/22/19 Capital Project Update
Posted on 03/22/2019

The following is an update for Phase 1, 2, & 3 of the Dryden Capital Improvement Project.

Work week of 3/18/19 – 3/122/19

Phase 1  

o   Whitmore fence installing foundations, poles and netting on new backstops at the HS/MS

Phase 2

o   Brush and tree clearing are complete, started stump grinding and clean up

Phase 3

o   With the exception of the main ceiling demo inn C13 is largely complete

o   Entrance canopy was demoed and continues to be broken up and disposed of

o   All trees scheduled to be removed at DES have been removed and cleaned up

o   The existing Kiln has been relocated to the new art room and the temporary sink is in place

o   New cooler slab recess has been cut into the existing floor in room #A11 and its removal started

o   Building has been posted for the required ten day posting prior to asbestos abatement

Work week of 3/18/19 – 3/22/19

Phase 1

o   Whitmore fence will continue work on the new backstops poles and netting

Phase 2

o   Bolands will grind all tree stumps clean up the mulch and the start the installation of the stabilized construction entrance off of Mott road

Phase 3

o   Remainder of entrance canopy will be broken up and removed

o   Room #A11 floors areas will be removed and the new freezer area excavated to grade for the slab recess

o   Several heat, plumbing and electrical lines not identified on the drawings will need to be relocated, Hunts engineer has reviewed and we hope to get some of that work out of the way while we are on hold waiting for the asbestos abatement