5/6/19 Capital Project Update

5/6/19 Capital Project Update
Posted on 05/06/2019

The following is an update for Phase 1, 2, & 3 of the Dryden capital Improvement project, I apologize for the lack of pictures I am having issues transferring them off my phone. 

Work week of 4/29/19 – 5/3/19

Phase 1
Hale roofing has continued work on the finish metal roof trim and is on track to be done in about 3 weeks.  Nagle has started laying down the new track surface while dodging the rain all week.  Boland’s has stayed on site despite the rain and continued work on the new fields laying underdrain and setting poles and foundations.

Phase 2
o Boland’s has been building the site staging area along Mott road and finished up with the rough grading.

Phase 3
Asbestos removal was completed in the boys locker room and demolition of the remainder of the room has continued all week.
o Kitchen demolition has progressed all week with most of the walls, ceilings and cooler removed.
o The corridor ceiling between the kitchen and A11 has been removed.
o Remaining walls and duct work were removed from A11.
o Nelorp has started the electrical rough in for the cooler space and been demolishing existing electrical systems in the boiler room and kitchen.
o Siracusa has been doing HVAC and plumbing demo in the boiler room.

Work week of 5/6/19 – 5/10/19

Phase 1
o Nagel will continue with installing the new track surface as weather permits.
o Hale roofing will continue with the install of roofing metal and detail work.
o Boland's will continue to work on the new athletic fields and dugouts.

Phase 2
o Boland's will complete the staging area and materials for underground utilities will start to be delivered. Edger will be mobilizing the following week to start foundations for the new building.

Phase 3
o Demolition on the remaining ceiling and MEP systems in C13.
o General demolition in the boys locker room, saw cut floors for plumbing underground.
o Kitchen demolition remaining walls, ceilings and MEP systems.
o Kitchen floors will be saw cut for underground plumbing work.